Monday, March 28, 2011

Design Elements Come to Life!


Welcome to TrueNorth!

Work has begun on some of the design elements of our new space!  The "floating" conference room that will be a focal point in our new lobby is starting to take shape, literally!

Wednesday, March 23, 2011

What a difference a day makes...

The steel for the second story ceiling and roof is being erected today, more visible progress!



Tuesday, March 22, 2011

Spring Ahead!

With the decent weather we have been having it has allowed our construction crews to make some great progress!  Steel is becoming a more and more common sight both around the job site and being placed in and around the building.

Steel placed for support walls


Do you remember when the library lobby looked like this?! 



Take a look at it today...


We keep hoping Mother Nature deals the cards in our favor this Spring, the good weather is a must when trying to reach our ever so quickly approaching deadline!

Wednesday, March 9, 2011

Our "Story" Begins...

All stories are built upon a strong foundation.  This next chapter of the TrueNorth story is exciting as we begin to build out the 2nd story of our new building that has the strong foundation of the building once known as the Cedar Rapids Public Library now supporting us!
Steel beams being placed on the outside perimeter of the second floor

Wednesday, March 2, 2011

Off with the roof!

Our contractors have started to remove the old roof to allow for the second story framing!  Progress continues throughout the whole building, we should start seeing more exterior changes each day!  For those of us in Iowa it is also a sign that nicer weather is right around the corner!